Para-Port Retrofit at Bangor International Airport

February 20, 2026


Summary

A hydraulic, cable-lifted steel door failed at Bangor International Airport (BGR). The airport suddenly had a 10,000 sq. ft. hangar out of service. The airport faced revenue loss from an unusable hangar. Repair companies were unwilling to assume the liability and risk of servicing a damaged door. BGR needed a dependable, long-term replacement that could restore operations quickly and perform in Maine’s extreme weather efficiently and flawlessly for many decades to come.

Chiles Contracting presented a premium solution at a competitive price by partnering with Para-Port® Doors, whose proven product design enabled an efficient construction process and rapid installation. After evaluating multiple door systems, Bangor International Airport selected Para-Port® Doors for their reliability, energy efficiency, and retrofit expertise.

“Para-Port’s product design makes installation straightforward, seamless, and without major structural changes. Every trade is able to work efficiently. The door design supports a rapid and cost-effective retrofit.”

-Andrew Chiles, President of Chiles Contracting

 

Challenges

Maintenance

Repair companies refused to service the hydraulic, cable-lifted steel hangar door due to liability and safety of the hydraulic door.

 

Urgency

The door failure meant the hangar was no longer generating revenue on a 10,000 sq. ft. hangar. Additionally, an emergency service vehicle was trapped in the hangar.

 

Bangor International Airport needed an immediate, energy-efficient, and low-cost solution built to last many decades. BGR evaluated doors based on engineering integrity and lifetime performance, as well as hangar operating costs.

 

Solution

The Para-Port® Door integrated seamlessly into the existing structure. In just 10 weeks, Chiles Contracting completed engineering, minor opening modifications, and a Para-Port® Door was installed and fully operational.

 

“The Para-Port® system was implemented with minimal structural changes to the hangar. The install timeline was rapid, with only 8-weeks from contracted to install. The translucent design has improved the lighting of the structure even with a north facing door.”

— Francis Robbins, Airport Director, Bangor Int’l Airport

 

With fewer moving parts and no hydraulics, Bangor International Airport eliminated hydraulic door maintenance issues. Para-Port® Door provided BGR with a product design that yields excellent energy efficiency with tight seals, minimizing air exchange when operating the door. An efficient door system with a tension fabric PVC curtain now shelters the hangar. BGR’s hangar door always opens, regardless of ice, snow, or wind.

 

Timeline

July 3, 2025

   Chiles Contracting visited and began engineering for bid.
   July 2, 2025   Contract for Para-Port® Doors executed with Chiles Contracting
   July 18, 2025   Demolition complete. Opening modification begins.
   July 25, 2025   Steelwork and electrical work completed.
   Aug 28, 2025   A new Para-Port® Door is installed and completely operational.